Turner Construction Co., the university’s construction manager for the new academic complex, reports that as of Mar. 14, 2007, the project is on schedule and within budget. It is 70 percent complete. Drywall in the new academic complex is 90 percent complete, with painting in progress.
The university broke ground for the new home of the College of Business Administration and College of Education on May 2, 2006. The complex is scheduled to open in August of 2007.
Construction photos (courtesy of Turner Construction Co.).
Please view our live Web cam for the most up-to-date images of the construction site.
|